SED posted a notice on the Facilities Planning website that all submissions for Preliminary Reviews and BAU Recalculations will be prescreened. Their guidance noted that submissions should not be mailed to the Office of Facilities Planning until:
- Letter of Intent (LOI) has been sent in,
- A project number has been assigned, and
- All the items in the PDF checklist (link below) are complete.
A review number will not be assigned, and the PR submission will not be put in the PR review queue, until all the items on the checklist are received and deemed complete.
Upon paper submission, please email the submission package, EXCEL document with the room list, and any questions to the Fiscal Associate assigned to your district. If you need to review who the Fiscal Associate is assigned to your district, please see their list.
Preliminary Review Checklist can be found here.